This article describes different ways how Buyer users can do Planned Allocation/Split Awarding for received offers from Suppliers.

If there is a need to divide the awarding of items among several suppliers, it can be done in the following ways:

- on Pivot Table tab
- on Supplier Analysis tab
- on Scenarios tab

 

Method 1: Using the Pivot Table Tab

  1. Go to the Pivot Table Tab: Open the Pivot Table Tab within the request.

  2. Select the Item: Click the three-dot icon next to the item name to open the list of actions.

    Screenshot 2025-11-11 at 11.48.07
  3. Click "Split Awarding": Select the Split Awarding button from the actions menu.

  4. Choose Split Type:

    • Select whether you want to split the quantity by percentage or by a specific unit of measure.

    • Enter the quantity or percentage you want to allocate to each selected supplier.

      Screenshot 2025-11-11 at 11.49.53
  5. Confirm: Once you’ve entered the required quantities, confirm your action, and the system will divide the awarding accordingly.

    Screenshot 2025-11-11 at 11.52.15

Method 2: Using the Supplier Analysis Tab

  1. Go to the Supplier Analysis Tab: Open the Supplier Analysis Tab within the request.

  2. Click "Split Awarding": Locate the item and click the Split Awarding button next to the item name (cake icon).

    Screenshot 2025-12-11 at 11.23.50
  3. Choose Split Type:

    • Select to split the quantity by percentage or a specific unit of measure.

    • Enter the desired quantity per each selected supplier.

      Screenshot 2025-12-11 at 11.26.44
  4. Confirm: Confirm your inputs, and the awarding will be divided as specified.

    Screenshot 2025-12-11 at 11.27.12


Method 3. On Scenarios tab

  1. Go to the Scenarios Tab: Open the Scenarios Tab within the request.

  2. Click "Create Scenario": Create a new scenario, create a name for the scenario and click the button `Add new set`. Then click button `Add split quantities`.

    Screenshot 2025-12-11 at 11.39.35

3. Enter the percentage for planned allocation and see how Item list and such data as Total Value, Savings, Coverage, Selected suppliers etc change as you insert percentage.

ezgif.com-video-to-gif-converter-Dec-11-2025-11-55-10-0975-AM

Within Scenarios, you can create several Sets with different percentage rates to see how different Sets influence final awarding results.

Screenshot 2025-12-11 at 11.43.15


It is also possible to combine `Split quantities` function with other filters to view expected results. 

Screenshot 2025-12-11 at 11.46.08

If applied filters don`t match planned allocation, the system will show warning:

Screenshot 2025-12-11 at 11.44.33


Modifying or Canceling a Planned Allocation

If it is necessary to change or cancel a planned allocation, simply click the Cross Icon in the planned allocation section or click Bin Icon next to Split Awarding section in the left-side menu from the item name. This will allow you to adjust or remove the allocation as needed.